FourSquares….. and a certain amount of doubt

Project Phases

Phase 1
Strip Down Walls and Flooring.
Replace gutters (to eliminate water damage)
Status:  Complete.
Phase 2
Structural Support
Electrical
Plumbing
HVAC
Insulation and Dry Wall
Windows
Status:  Complete.
Phase 3
Kitchen Install
Bathroom Installs - Powder room and Upstairs
Paint Walls
Finish Ceilings (if tiled, etc)
Finish Floors
Status:  Not there yet!
(at this point we can move in!)
Status: Not there yet!
Phase 4
Addition of Family room, Master bedroom, Master bathroom (apply for new permit)
New Siding
Solar Panels
Landscaping and Raingarden
Fencing
Status: Only in dreams!